Report for units that engine not working more than 2 days

Тема: Report for units that engine not working more than 2 days

Hello Dears
Our client needed a report for units that IT'S Engine not working for more than 2 days. is that report available?
Thanks

2

Report for units that engine not working more than 2 days

Re: Report for units that engine not working more than 2 days

Hello,

Probable solution:
1) Create a digital custom sensor to control ignition off status. Let's say this parameter is "ign". Then use the following expression: const1-ign
2) Create a report template with a table "Digital sensors" including columns "Sensor", "Duration" and others you want.
3) Switch to the tab "Settings" and add some intervals filtration. First of all use the name of the sensor from step 1 as sensor mask. After that set min duration filter to 48:00:00.

@ Oleg Zharkovsky
Customer Service / Quality Control and Training
"Timely is the best. But still better late than never."
3

Report for units that engine not working more than 2 days

Re: Report for units that engine not working more than 2 days

can i have duration for more than 100 hour?

4

Report for units that engine not working more than 2 days

Re: Report for units that engine not working more than 2 days

hasan.ahmed пишет:

can i have duration for more than 100 hour?

The table shows actual duration of the digital sensor active state, so it can be more than 100 hours.
But filtration by duration has maximum bound about 99 hours.

If you want to filter more than 100 hours, please direct you request to the special forum branch.

@ Oleg Zharkovsky
Customer Service / Quality Control and Training
"Timely is the best. But still better late than never."
5

Report for units that engine not working more than 2 days

Re: Report for units that engine not working more than 2 days

Hello Dears
Our client needed a report for units that IT'S Engine not working for more than 2 days. is that report available?
Thanks

Jerry
6

Report for units that engine not working more than 2 days

Re: Report for units that engine not working more than 2 days

Belinda11 пишет:

Hello Dears
Our client needed a report for units that IT'S Engine not working for more than 2 days. is that report available?
Thanks

the Gurtam support  already replied on this question.